From The Bismarck Tribune, data points:- first phase to be complete in October
- second phase to begin next season
- federal funding: $10 million discretionary funds annually and $2 million in entitlement funding annually
- city agreed to $11 million
- airport had $6 million in reserves
- since then, bid amounts for the now $49 million second phase have decreased by $4 million; federa funding has increased by $6 million in extra discretionary funds
- bottom line: about $10 million "to the good"
- next phase: about $15 million
- total project cost: $65 million
Thus Article Update On New Runway At Bismarck Airport -- September 23, 2017
That's an article Update On New Runway At Bismarck Airport -- September 23, 2017 This time, hopefully can give benefits to all of you. well, see you in posting other articles.
You are now reading the article Update On New Runway At Bismarck Airport -- September 23, 2017 with the link address https://mylivemyidea.blogspot.com/2017/09/update-on-new-runway-at-bismarck.html
0 Response to "Update On New Runway At Bismarck Airport -- September 23, 2017"
Post a Comment