Title : Pipelines Beating Estimates -- August 3, 2018
link : Pipelines Beating Estimates -- August 3, 2018
Pipelines Beating Estimates -- August 3, 2018
Jobs:- new jobs added: less than forecast
- previous revised upward from 241,000 to 248,000
- unemployment ticks down to 3.9%
- labor force participation: 62.9%
- market yawns
Earnings: fast and furious --
***************************
Back to the Bakken
Wells coming off confidential list today:
34057, conf, BR, Rink 8-1-5MBH, Pershing, no production data,
33931, conf, BR, Three Sons 1A TFH-ULW, BR, Charlson,
33395, conf, WPX, Hidatsa North 14-23HB, Reunion Bay, no production data,
33388, conf, Crescent Point Energ, CPEUSC Paopao 7-35-26-158N-100W MBH, Dublin, no production data,
Active rigs:
$68.93→ | 8/3/2018 | 08/03/2017 | 08/03/2016 | 08/03/2015 | 08/03/2014 |
---|---|---|---|---|---|
Active Rigs | 64 | 58 | 34 | 74 | 194 |
RBN Energy: a new drill down report on Permian gas takeaway constraints and their effects.
A big push is on to mitigate and ultimately fix the Permian’s natural gas takeaway constraints, which in recent months have widened the price spread between gas at Waha and at Henry Hub to levels not seen in years. Despite the efforts to quickly add incremental capacity to existing pipelines and build greenfield pipes, however, the momentum behind Permian crude production growth — and, with it, the production of more associated gas — make a months-long blowout in the Waha basis in 2019 a good bet. Questions about the degree and duration of that basis pain and the amount of new pipeline capacity that will be needed (and how soon) can only be answered by taking a detailed look at what’s been happening and what’s being planned. Today, we discuss highlights from our new 24-page report on Permian gas takeaway constraints and their effects.
Thus Article Pipelines Beating Estimates -- August 3, 2018
That's an article Pipelines Beating Estimates -- August 3, 2018 This time, hopefully can give benefits to all of you. well, see you in posting other articles.
You are now reading the article Pipelines Beating Estimates -- August 3, 2018 with the link address https://mylivemyidea.blogspot.com/2018/08/pipelines-beating-estimates-august-3.html
0 Response to "Pipelines Beating Estimates -- August 3, 2018"
Post a Comment