First, a little background, because I think the route will be along some of the existing easements.To get an idea of the geographical area we're talking about, you may want to take another look at this noted posted just a few days ago regarding "the Voyager."
From the BusinessWire, a Berkshire Hathaway Company:
- The True companies, based in Casper, WY:
-
- Bridger Pipeline LLC
- Belle Fourche Pipeline Company
- Butte Pipe Line Company
- Bridger Pipeline LLC owns and operates:
-
- the Poplar System in eastern Montana
- the Four Bears Pipeline System in North Dakota
- the Parshall Gathering System in Wyoming
- the Powder River System in Wyoming
- Belle Fourche Pipeline Company gathers and transports crude oil in:
-
- the Williston Basin of western North Dakota
- the Powder River Basin of Wyoming
- Butte Pipe Line Company owns the transmission line from Baker, MT, to Guernsey, WY
- joint venture between Philllips 66 and Bridger Pipeline LLC
- Liberty Pipeline
- origin: "from the Rockies and the Bakken production areas"
- terminus: "Corpus Christi, Texas
- initial capacity: 350,000 bopd; with ability to expand
- anticipated in-service date: 4Q20
- announced the Red Oak Pipeline
- origin: Cushing, OK
- terminus: Corpus Christi, Houston, and Beaumont (TX)
- initial throughput: 400,000 bopd with ability to expand
- anticipated in-service date: 4Q20
****************************************
Meanwhile, The Keystone XL Is Stopped Again
I suppose if you want to read the article (at this link), you can. But it's the same old thing. Bottom line: Keystone XL construction has been stopped, putting hundreds of hard-working, salt-of-the-earth men and women out of work.
The US district judge announced his ruling two days after the mid-term elections in which the Democratic candidate for US Senate won by a very, very narrow margin.
*********************************
Meanwhile, The DAPL Is At Jeopardy In Two Courts
Previously posted:
- Minnesota (for North Dakota landowners)
- Iowa
Thus Article New Bakken Pipeline Announced; Meanwhile A Montana Judge Kills The Keystone XL -- November 10, 2018
That's an article New Bakken Pipeline Announced; Meanwhile A Montana Judge Kills The Keystone XL -- November 10, 2018 This time, hopefully can give benefits to all of you. well, see you in posting other articles.
You are now reading the article New Bakken Pipeline Announced; Meanwhile A Montana Judge Kills The Keystone XL -- November 10, 2018 with the link address https://mylivemyidea.blogspot.com/2018/11/new-bakken-pipeline-announced-meanwhile.html
0 Response to "New Bakken Pipeline Announced; Meanwhile A Montana Judge Kills The Keystone XL -- November 10, 2018"
Post a Comment